PROJECT TITLE       PROJ. NO.   PROJECT CLASSIFICATION  
Bay Ridge WST   Water
 
DESCRIPTION:                  
The Bay Ridge Water Storage Tower has been proposed for several years.  The land for the site was donated to MetCom by the developer before any houses were built in that area.   The anticipated tower will have a capacity of 350,000 gallons.  The contract for construction will be bid in CY 2008.  The site is adjacent to County owned property near the Great Mills Public Swimming Pool.
   
   
   
   
   
   
   
   
   
   
   
   
   
PLANNING JUSTIFICATION:  
In 2002 an engineering study investigated the water needs of the greater Lexington Park/Great Mills area.  The study found the area deficient in water storage and determined that the area required over 1 million gallons for domestic use and fire protection. Two possible tower sites were identified, however, no new storage tanks were constructed.  The immediate area around the site is being developed and requires additional storage.  This elevated tank will supply 350,000 gallons for fire protection and domestic use.
LOCATION:  
8th Sanitary District                  
PROJECT TITLE       PROJ. NO.   PROJECT CLASSIFICATION  
Bay Ridge WST   Water
COST CENTER Sewer Water Total Project            
Planning $0 $36,800 $36,800            
Engineer / Design $0 $145,000 $145,000            
Land Acquisition $0 $0 $0            
Construction $0 $591,000 $591,000            
Overhead $0 $77,200 $77,200            
Other $0 $0 $0            
Total $0 $850,000 $850,000            
                   
Service Area Expansion% 0.0% 0.0%              
Capital Facilities Expansion% 0.0% 100.0%              
Upgrade/Replacement% 0.0% 0.0%              
Other Sources% 0.0% 0.0%              
  Spent     Five Year Capital Improvement Budget  Total
APPROPRIATION  FY07 FY 2008 FY 2009 FY 2010 FY 2011 FY 2012 Project
SEWER $0 $0 $0 $0 $0 $0 $0
WATER $0 $850,000 $0 $0 $0 $0 $850,000
TOTAL COSTS   $0 $850,000 $0 $0 $0 $0 $850,000
FUNDING SOURCE Spent     Five Year Capital Improvement Budget  Total
FUNDS: FY07 FY 2008 FY 2009 FY 2010 FY 2011 FY 2012 Project
LOANS $0 $0 $0 $0 $0 $0 $0
BONDS $0 $0 $0 $0 $0 $0 $0
GRANTS $0 $0 $0 $0 $0 $0 $0
NAVY $0 $0 $0 $0 $0 $0 $0
RESERVES $0 $0 $0 $0 $0 $0 $0
COUNTY FUNDS $0 $0 $0 $0 $0 $0 $0
STATE FUNDS $0 $0 $0 $0 $0 $0 $0
FEDERAL FUNDS $0 $0 $0 $0 $0 $0 $0
OTHER SOURCES $0 $0 $0 $0 $0 $0 $0
specify: $0 $0 $0 $0 $0 $0 $0
TOTAL FUNDS   $0 $0 $0 $0 $0 $0 $0
CONTINUATION SHEET
PROJECT TITLE       PROJ. NO.   PROJECT CLASSIFICATION
     
OTHER BACKGROUND INFORMATION/COMMENTS:              
 
DISCUSSION OF CHANGE FROM FY 2007 APPROVED BUDGET/PLAN:  
.  
IMPACT ON ANNUAL OPERATING BUDGET
INCREMENTAL OPERATING COSTS  
DESCRIPTION FY 2008 FY 2009 FY 2010 FY 2011 FY 2012 FY 2013  
STAFFING -FTEs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00  
               
PERSONAL SERVICES COSTS $0.00 $0.00 $0.00 $0.00 $0.00 $0.00  
CONTRACTED SERVICES $0.00 $0.00 $0.00 $0.00 $0.00 $0.00  
SUPPLIES & MATERIALS $0.00 $0.00 $0.00 $0.00 $0.00 $0.00  
UTILITIES $0.00 $0.00 $0.00 $0.00 $0.00 $0.00  
FURNITURE & EQUIPMENT $0.00 $0.00 $0.00 $0.00 $0.00 $0.00  
OTHER (describe significant items) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00  
TOTAL COSTS   $0.00 $0.00 $0.00 $0.00 $0.00 $0.00  
DISCUSSION OF OPERATING BUDGET IMPACT:                
   
   
   
OTHER IMPACT ON OPERATIONS/OPERATING BUDGET: