| PROJECT TITLE | PROJ. NO. | PROJECT CLASSIFICATION | |||||||
| Great Mills Well -South End of Great Mills Rd. | Water | ||||||||
| DESCRIPTION: | |||||||||
| The Great Mills area is currently served by the Lexington Park system. While there is one small well in the Piney Point/Nanjemoy aquifer the area is being developed and needs a closer water source. The well will serve new developments such as Cecil Mills Subdivision, Cecil Mills Town Homes, Elizabeth Hills Subdivision and the future unknown growth in that immediate area. The size and exact location of the well is yet to be determined. | |||||||||
| PLANNING JUSTIFICATION: | |||||||||
| The Great Mills area is growing and most of the water supplied to that area comes from wells that are 2-3 miles away. This causes pressure problems and raises water quality concerns caused by the difficulty maintaining consistent chorine residuals over such a large area. A new well in the Great Mills area will support existing customers as well as potential future customers. | |||||||||
| LOCATION: | |||||||||
| 8th Sanitary District | |||||||||
| PROJECT TITLE | PROJ. NO. | PROJECT CLASSIFICATION | |||||||
| Great Mills Well -South End of Great Mills Rd. | Water | ||||||||
| COST CENTER | Sewer | Water | Total Project | ||||||
| Planning | $0 | $12,000 | $12,000 | ||||||
| Engineer / Design | $0 | $25,000 | $25,000 | ||||||
| Land Acquisition | $0 | $0 | $0 | ||||||
| Construction | $0 | $213,000 | $213,000 | ||||||
| Overhead | $0 | $25,000 | $25,000 | ||||||
| Other | $0 | $0 | $0 | ||||||
| Total | $0 | $275,000 | $275,000 | ||||||
| Service Area Expansion% | 0.0% | 0.0% | |||||||
| Capital Facilities Expansion% | 0.0% | 50.0% | |||||||
| Upgrade/Replacement% | 0.0% | 50.0% | |||||||
| Other Sources% | 0.0% | 0.0% | |||||||
| Spent | Five Year Capital Improvement Budget | Total | |||||||
| APPROPRIATION | FY07 | FY 2008 | FY 2009 | FY 2010 | FY 2011 | FY 2012 | Project | ||
| SEWER | $0 | $0 | $0 | $0 | $0 | $0 | $0 | ||
| WATER | $0 | $0 | $275,000 | $0 | $0 | $0 | $275,000 | ||
| TOTAL COSTS | $0 | $0 | $275,000 | $0 | $0 | $0 | $275,000 | ||
| FUNDING SOURCE | Spent | Five Year Capital Improvement Budget | Total | ||||||
| FUNDS: | FY07 | FY 2008 | FY 2009 | FY 2010 | FY 2011 | FY 2012 | Project | ||
| LOANS | $0 | $0 | $0 | $0 | $0 | $0 | $0 | ||
| BONDS | $0 | $0 | $0 | $0 | $0 | $0 | $0 | ||
| GRANTS | $0 | $0 | $0 | $0 | $0 | $0 | $0 | ||
| NAVY | $0 | $0 | $0 | $0 | $0 | $0 | $0 | ||
| RESERVES | $0 | $0 | $0 | $0 | $0 | $0 | $0 | ||
| COUNTY FUNDS | $0 | $0 | $0 | $0 | $0 | $0 | $0 | ||
| STATE FUNDS | $0 | $0 | $0 | $0 | $0 | $0 | $0 | ||
| FEDERAL FUNDS | $0 | $0 | $0 | $0 | $0 | $0 | $0 | ||
| OTHER SOURCES | $0 | $0 | $0 | $0 | $0 | $0 | $0 | ||
| specify: | $0 | $0 | $0 | $0 | $0 | $0 | $0 | ||
| TOTAL FUNDS | $0 | $0 | $0 | $0 | $0 | $0 | $0 | ||