PROJECT TITLE       PROJ. NO.   PROJECT CLASSIFICATION  
Hickory Hills Raising and Painting   Water
 
DESCRIPTION:                  
In the greater Lexington Park water system there are currently three pressure zones.  Each zone is isolated from the others by altitude valves or by gate valves.  This prevents one zone over flowing the tanks in the adjacent zone.  Having several pressure zones increase maintenance cost, causes customer complaints (pressure to low or too high),  and restricts the even distribution of water from the supply wells. To correct this situation two water storage units must be elevated to match the highest tower.   The Hickory Hills water storage tank is approximately 46 feet lower than the adjacent water tower at Wildewood.  The HHWST can be raised to the same elevation as Wildewood for less money than building a new one of the same size.
   
   
   
   
   
   
   
   
   
   
   
   
   
PLANNING JUSTIFICATION:  
It is less expensive to raise the existing tower than to construct a new one or use continuous booster stations. Additional elevated water storage is needed in this area of Lexington Park to serve existing and future customers.
LOCATION:  
Eighth Sanitary District                  
PROJECT TITLE       PROJ. NO.   PROJECT CLASSIFICATION  
Hickory Hills Raising and Painiting   Water
COST CENTER Sewer Water Total Project            
Planning (5%) $0 $15,000 $15,000            
Engineer / Design $0 $15,000 $15,000            
Land Acquisition $0 $0 $0            
Construction $0 $550,000 $550,000            
Overhead(10%) $0 $20,000 $20,000            
Other $0 $0 $0            
Total $0 $600,000 $600,000            
                   
Service Area Expansion% 0% 0%              
Capital Facilities Expansion% 0% 0%              
Upgrade/Replacement% 0% 100%              
Other Sources% 0% 0%              
  Spent     Five Year Capital Improvement Budget  Total
APPROPRIATION  FY07 FY 2008 FY 2009 FY 2010 FY 2011 FY 2012 Project
SEWER $0 $0 $0 $0 $0 $0 $0
WATER $0 $600,000 $0 $0 $0 $0 $600,000
TOTAL COSTS   $0 $600,000 $0 $0 $0 $0 $600,000
FUNDING SOURCE Spent     Five Year Capital Improvement Budget  Total
FUNDS: FY07 FY 2008 FY 2009 FY 2010 FY 2011 FY 2012 Project
LOANS $0 $0 $0 $0 $0 $0 $0
BONDS $0 $0 $0 $0 $0 $0 $0
GRANTS $0 $0 $0 $0 $0 $0 $0
NAVY $0 $0 $0 $0 $0 $0 $0
RESERVES $0 $0 $0 $0 $0 $0 $0
COUNTY FUNDS $0 $0 $0 $0 $0 $0 $0
STATE FUNDS $0 $0 $0 $0 $0 $0 $0
FEDERAL FUNDS $0 $0 $0 $0 $0 $0 $0
OTHER SOURCES $0 $0 $0 $0 $0 $0 $0
specify: $0 $0 $0 $0 $0 $0 $0
TOTAL FUNDS   $0 $0 $0 $0 $0 $0 $0