PROJECT TITLE       PROJ. NO.   PROJECT CLASSIFICATION  
Navy System Upgrade   Sewer & Water
 
DESCRIPTION:                  
Since the mid-1990's the Department of Defense has initiated a program of outsourcing base operations and housing.  The Department of the Navy solicited bidders to purchase and operate the water and sewer system on Patuxent River Naval Air Station.  MetCom has been chosen as the finalist to take over these operations.  This process started in 2001, the final decision is due in December 2007.  If MetCom's proposal is accepted by the Navy, it would be initiated within six months of award.  Extensive investigation of the existing systems was conducted and the cost associated with this developed. The main components are the installation of a SCADA system for both water and sewer stations; upgrading of sewer electric panels and installing high efficiency pumps; extensive metering of buildings and housing areas and rehabilitation of several sewer lines.
   
   
   
   
   
   
   
   
   
   
   
   
PLANNING JUSTIFICATION:  
This project is only necessary if MetCom's proposal to the Navy is accepted.  To operate the system efficiently it is necessary to upgrade and improve the system.  All costs associated with the upgrade would be back charged to the Navy over an extended period.
LOCATION:  
8th Sanitary District                  
PROJECT TITLE       PROJ. NO.   PROJECT CLASSIFICATION  
Navy System Upgrade    
COST CENTER Sewer Water Total Project            
Planning $60,000 $56,500 $116,500            
Engineer / Design $65,000 $65,500 $130,500            
Land Acquisition $0 $0 $0            
Construction $1,300,000 $1,078,000 $2,378,000            
Overhead $130,000 $120,000 $250,000            
Other $0 $0 $0            
Total $1,555,000 $1,320,000 $2,875,000            
                   
Service Area Expansion% 0.0% 0.0%              
Capital Facilities Expansion% 0.0% 0.0%              
Upgrade/Replacement% 0.0% 0.0%              
Other Sources% 100.0% 100.0%              
  Spent     Five Year Capital Improvement Budget  Total
APPROPRIATION  FY07 FY 2008 FY 2009 FY 2010 FY 2011 FY 2012 Project
SEWER $0 $0 $1,555,000 $0 $0 $0 $1,555,000
WATER $0 $0 $1,320,000 $0 $0 $0 $1,320,000
TOTAL COSTS   $0 $0 $2,875,000 $0 $0 $0 $2,875,000
FUNDING SOURCE Spent     Five Year Capital Improvement Budget  Total
FUNDS: FY07 FY 2008 FY 2009 FY 2010 FY 2011 FY 2012 Project
LOANS $0 $0 $0 $0 $0 $0 $0
BONDS $0 $0 $0 $0 $0 $0 $0
GRANTS $0 $0 $0 $0 $0 $0 $0
NAVY $0 $0 $0 $0 $0 $0 $0
RESERVES $0 $0 $0 $0 $0 $0 $0
COUNTY FUNDS $0 $0 $0 $0 $0 $0 $0
STATE FUNDS $0 $0 $0 $0 $0 $0 $0
FEDERAL FUNDS $0 $0 $0 $0 $0 $0 $0
OTHER SOURCES $0 $0 $0 $0 $0 $0 $0
specify: $0 $0 $0 $0 $0 $0 $0
TOTAL FUNDS   $0 $0 $0 $0 $0 $0 $0