PROJECT TITLE       PROJ. NO.   PROJECT CLASSIFICATION  
Piney Point Water Storage Tank   Water
 
DESCRIPTION:                  
Design and construction of a elevated water storage tank for the Piney Point Water System.
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
PLANNING JUSTIFICATION:  
 The current Piney Point Water System consists of one 110gpm well, a reserve well, and a 30,000 gallon ground storage tank. Due to growth in the Piney Point Town Center, a new elevated storage tank is needed to ensure adequate water supply to meet domestic demand and fire supression needs. 
LOCATION:  
Sanitary District 5                  
PROJECT TITLE       PROJ. NO.   PROJECT CLASSIFICATION  
Piney Point Water Storage Tank   Water
COST CENTER Sewer Water Total Project            
Planning  $0 $28,000 $28,000            
Engineer / Design $0 $50,000 $50,000            
Land Acquisition $0 $0 $0            
Construction $0 $650,000 $650,000            
Overhead $0 $72,000 $72,000            
Other $0 $0 $0            
Total $0 $800,000 $800,000            
                   
Service Area Expansion% 0% 0%              
Capital Facilities Expansion% 0% 0%              
Upgrade/Replacement% 0% 100%              
Other Sources% 0% 0%              
  Spent     Five Year Capital Improvement Budget  Total
APPROPRIATION  FY07 FY 2008 FY 2009 FY 2010 FY 2011 FY 2012 Project
SEWER $0 $0 $0 $0 $0 $0 $0
WATER $0 $50,000 $450,000 $300,000 $0 $0 $800,000
TOTAL COSTS   $0 $50,000 $450,000 $300,000 $0 $0 $800,000
FUNDING SOURCE Spent     Five Year Capital Improvement Budget  Total
FUNDS: FY07 FY 2008 FY 2009 FY 2010 FY 2011 FY 2012 Project
LOANS $0 $0 $0 $0 $0 $0 $0
BONDS $0 $0 $0 $0 $0 $0 $0
GRANTS $0 $0 $0 $0 $0 $0 $0
NAVY $0 $0 $0 $0 $0 $0 $0
RESERVES $0 $0 $0 $0 $0 $0 $0
COUNTY FUNDS $0 $0 $0 $0 $0 $0 $0
STATE FUNDS $0 $0 $0 $0 $0 $0 $0
FEDERAL FUNDS $0 $0 $0 $0 $0 $0 $0
OTHER SOURCES $0 $0 $0 $0 $0 $0 $0
specify: $0 $0 $0 $0 $0 $0 $0
TOTAL FUNDS   $0 $0 $0 $0 $0 $0 $0