PROJECT TITLE       PROJ. NO.   PROJECT CLASSIFICATION  
St Georges Park Sewer System Improvements 5-9-S Sewer
 
DESCRIPTION:                  
      The St. Georges Park Sewer Improvements Project is an effort to provide service for 118 EDU’s that have currently been allocated against the capacity of the Sheehan Pumping Wastewater Station. This does not provide for the EDU’s on the wait list or others wanting capacity in the Sheehan Station. The station currently has adequate pumping and wet well capacities to service the 118 allocated EDU’s.  The following system improvements must be made to allow for these 118 EDU's to connect to service. Needed items are, approximately 750 feet of 3” HDPE to include the associated appurtenances and connections. The newly installed lines will be servicing proposed developments to divert flow from lines which are now over committed and to improve service and reliability to existing customers. The County wide Facility Plan will identify the number of EDU's that need service in this area and the upgrades necessary to provide adequate service to them.                                                                                                                                             
   
   
   
   
   
   
   
   
   
   
   
   
   
   
PLANNING JUSTIFICATION:  
 This project will afford the allocated EDU's the opportunity to connect. 
LOCATION:  
5th Sanitary District                  
PROJECT TITLE       PROJ. NO.   PROJECT CLASSIFICATION  
 St Georges Park Sewer System Improvements 5-9-S   Sewer
COST CENTER Sewer Water Total Project            
Planning  $2,719 $0 $2,719            
Engineer / Design $0 $0 $0            
Land Acquisition $0 $0 $0            
Construction $18,150 $0 $18,150            
Overhead $3,131 $0 $3,131            
Other $0 $0 $0            
Total $24,000 $0 $24,000            
                   
Service Area Expansion% 0% 0%              
Capital Facilities Expansion% 0% 0%              
Upgrade/Replacement% 0% 0%              
Other Sources% 100% 0%              
  Spent     Five Year Capital Improvement Budget  Total
APPROPRIATION  FY07 FY 2008 FY 2009 FY 2010 FY 2011 FY 2012 Project
SEWER $5,738 $18,262 $0 $0 $0 $0 $24,000
WATER $0 $0 $0 $0 $0 $0 $0
TOTAL COSTS   $5,738 $18,262 $0 $0 $0 $0 $24,000
FUNDING SOURCE Spent     Five Year Capital Improvement Budget  Total
FUNDS: FY07 FY 2008 FY 2009 FY 2010 FY 2011 FY 2012 Project
LOANS $0 $0 $0 $0 $0 $0 $0
BONDS $0 $0 $0 $0 $0 $0 $0
GRANTS $0 $0 $0 $0 $0 $0 $0
NAVY $0 $0 $0 $0 $0 $0 $0
RESERVES $0 $0 $0 $0 $0 $0 $0
COUNTY FUNDS $0 $0 $0 $0 $0 $0 $0
STATE FUNDS $0 $0 $0 $0 $0 $0 $0
FEDERAL FUNDS $0 $0 $0 $0 $0 $0 $0
OTHER SOURCES $0 $0 $0 $0 $0 $0 $0
specify: $0 $0 $0 $0 $0 $0 $0
TOTAL FUNDS   $0 $0 $0 $0 $0 $0 $0