|
MINUTES
PUBLIC
HEARING EVERGREEN PARK
SEWAGE COLLECTION SYSTEM
REPLACEMENT
JUNE 07, 2005
The meeting commenced at 7:00
p.m. In attendance were MetCom staff members Shreve, Pons, and Bryan.
Also in attendance were property owners as noted on the attached Sign-In
sheet.
Mr. Shreve introduced staff
prior to commencing a Power Point presentation on the proposed project.
A copy is attached to the Minutes, and is also available for viewing on
MetCom’s website at
www.metcom.org.
He noted that 26 houses are
involved in this project. However, a number of property-owner’s who are
building new houses on the left hand side of the entrance have
petitioned for connection to the proposed new system. This would be the
County’s decision, as a zoning change would have to be implemented to
allow this. In reply to a question from the floor, Mr. Shreve answered
that Evergreen Park is not a restricted use system.
Ms. Wilkinson questioned whether
permitting this would allow for development on the wooded, right-hand
side of the road. Mr. Shreve again replied that this would be the
County’s decision. Ms. Reid noted that she was informed this morning by
the Office of Land Use and Growth Management that five permits for five
lots were issued for that area. Mr. Shreve responded that, regardless of
this, they are currently excluded from the project and are zoned for “No
Planned Service”. Ms. Reid expressed her concern with additional
connections to an already failing pumping system. Mr. Shreve assured her
that the pipes in the ground, not the system, is at fault. At this
point, he invited Ms. Pons to present brief video clips on condition of
the pipes.
Ms. Pons briefly reviewed each
clip. These illustrated deterioration of the underground, old, vitrified
clay sewer pipes. Specifically, they showed a significant amount of
linear cracks in the ceilings; and disconnected joints separating to
allow root intrusion. Mr. Shreve agreed that this is one of the older
systems in the County, and that materials used at that time is vastly
inferior to that currently being utilized. Ms. Reid questioned why
MetCom permitted property owners’ to hook up originally, if they were
aware of the system’s shortcomings. Mr. Shreve replied that it was then
the material of choice; the system was in much better condition; and
MetCom wanted to keep their costs at a reasonable level.
Ms. Wilkinson questioned whether
the increased inflow would have any impact on drainage from bathtubs.
Mr. Shreve replied that this should not be the case. However, root
intrusions within service lines would cause problems.
A further property owner
questioned whether the problems with the lines would have any impact on
odor. Mr. Shreve agreed that it could occur for the following reasons:
if the trap is misaligned or out of shape and isn’t containing water
properly; the roof vent is clogged up; and there are faulty wax rings on
toilets.
Ms. Reid questioned why MetCom
did not maintain the system when they took control of it. Mr. Shreve
disagreed, stating that the proposed replacement is a problem relating
to the age of the system, and does not have anything to do with its
maintenance.
Mr. Shreve continued that
tonight’s hearing is to acknowledge the existing problem and to assure
property owners’ that MetCom proposes to resolve it. He stressed that
the numbers being presented tonight are only rough estimates. Once the
required Public Hearings have been completed, staff will request Board
approval to proceed with the engineering design. The successful
engineering firm will undertake a study to determine the best of the
eight options, with the least disruption to the community.
Mr. Shreve pointed out at this
time, that property owners’ within the Evergreen Park system have never
paid a debt service charge for the sewer pipe. However, MetCom’s laws
contained within St. Mary’s County Code, specifies that this charge must
be imposed for the new system. He also noted that the project will be
included within a proposed County-wide Uniform Debt Service (UDS)
charge. This will alleviate problems at locations where a significantly
high debt service charge exists. If everything proceeds according to
plan, staff anticipates implementing the UDS on July 1st,
2006. He warned, however, that there is no absolute guarantee that this
will happen; and noted that the proposed change in legislation was
submitted too late for inclusion in last year’s session. He concluded
that, under the UDS format, some bills will decrease; and some will
slightly increase, and noted that front footage assessment, and fees
relating to treatment plant capacity and water distribution will no
longer apply. At that point, everyone in the County who has public
sewer service will pay $9.04/month towards the UDS charge.
In reply to a question from the
floor regarding delay of the project until the proposed legislation is
implemented in July, Mr. Shreve said that this cannot be done, as it now
has highest priority as one of the two worst systems in the County.
In reply to a question regarding
the reason for different rates for different property owners, Mr. Shreve
said that the charges are based on front foot assessments. This charge
amounts to 67cents/front foot at this location, and will be billed on
completion of the project which is scheduled for March, 2006.
Mr. McCall requested provision
of a citation to the statute/ordinance referenced by Mr. Shreve,
regarding the requirement for Evergreen Park property owners’ to pay a
debt service charge on the new system, because they failed to do so
initially; and that Piney Point property owners’ are absolved from doing
so. Mr. Shreve will refer his request to Mr. King, Director of the
Commission, but noted that this is standard policy.
Mrs. Reid complained that when
property owners were originally connected to the system, she was
informed by MetCom staff, that they were responsible for the lines on
their properties, but that MetCom would be responsible for the main
system. Mr. Shreve agreed that this is correct. He stressed that MetCom
has maintained the main line to the best of its ability. Root cutters
have been utilized on a regular basis; trucks have been used to flush
lines out; and all normal prudent practices followed by every other
utility in the country has been observed.
Further Questions and
Answers are as follows:
What is the longevity of the
proposed new system?
This question will be discussed
with the design engineers.
Has an impact study been
undertaken to determine what would happen to the Bay, etc?
The impact is immediately
visible, so there has been no need to perform a study.
When the original system was
installed, the property owners picked up the cost when they bought the
property, which was connected to that system. Isn’t that essentially
the equivalent of a debt service charge?
No, because it was rolled over
into the cost of your house. It wasn’t a separate debt service charge to
pay for that system.
Why wait until the last few
years to replace the system?
Funding was a major part of the
decision.
When the pipes are installed,
would there be a policy regarding proximity of trees?
No. The PVC pipes which will be
utilized have bolted and glued flanges which will prohibit root
intrusion.
Will we continue to be hooked up
during the construction process?
This will be something for the
engineers to decide. We believe that the majority of service lines in
this area are in reasonable condition. However, some of the older ones
may need to be replaced. This will be at the homeowners’ expense.
Can the politicians help us?
No, I don’t think they’re going
to help you get it done without paying for it. However, if there are
hardship cases, the Commission has a deferral program for those
customers who meet the required criteria.
Will Delegate John Bohanan
sponsor the proposed legislative change?
Yes.
Who would be responsible to any
type of damage to the pipe?
This will be MetCom’s
responsibility.
When this proposed new system
eventually needs to be replaced, would property owners have to pay for
it again?
No. Once you pay a debt service
for it, you will not need to pay for it again. The exception would be
when the UDS becomes effective.
How would I know if I have clay
pipes?
The majority of service lines
in the area have PVC pipes. Only three people living on Evergreen Park
Drive have old iron pipes. This will be further investigated. It must
be noted here that it was not possible to film those pipes without a
clean-out.
Could we get better rates if we
used the same contractor?
Yes, possibly.
What about the big pipes that
sticks out into the yard? Can you make them shorter?
No. These are cleanouts. It
might be possible too make them a little shorter, but if they are
accidentally run over by a lawnmower, it could result in cracks.
I have a problem, because my
cleanout is situated very close to the driveway, and a family member hit
it with his vehicle.
We can investigate this. The
Engineer of choice will work with individual home owners to determine
the best location.
In conclusion, Mr. Shreve
reiterated that the presentation tonight is simply an estimate and
overview of the proposed project. The numbers are estimated on the
higher end of the scale and are approximately 85% accurate at this
point. However, he cannot guarantee that costs will not increase. Costs
with a 90-95% accuracy rate will be presented at the second Public
Hearing scheduled for September 21st.
The meeting concluded at 8:05
p.m.
 |