MD247 Loveville Road Water Main Replacement – Phase 1

New water main locations and properties affected by Phase 1 and Phase 2 of the project.

Background – Greenbrier Water Storage Tank

The existing system (known as the King Kennedy Water System) was built in the 1970’s as an independent stand-alone water system to serve King Kennedy Estates and the Loveville Acres residential developments.  MetCom subsequently assumed ownership and operation of this system, which serves approximately 63 properties.  Although only 50 years old (useful life is approximately 65 years for cement pipe), the water mains do not meet current MetCom specifications, are undersized and have ongoing maintenance issues.   Additionally, due to the line sizes, the fire hydrants are inoperable. 

Project Scope of Work

Phase 1:

​

Phase 1 of this project will affect customers inside the King Kennedy Subdivision on a portion of Independence Drive, Weber Street, and along the south side of MD247 from 26370 Loveville Road southwest to Independence Drive. This project will replace the existing 2”, 4”, and 8” diameter water lines with approximately 3,150 linear feet of 8” water main, new fire hydrants, and 22 new house connections to existing properties. Project construction is expected to start in Summer 2024.

Customer Impact

Traffic:

​

Residents in the area should expect minor traffic impacts during the construction. Please speak with our on-site construction inspector or call the project manager below with any traffic concerns. 

​

Water Service:

​

Residents in the area should expect minor interruptions to water service during construction. Residents will receive notice before any water service interruptions during the construction.

​

Sewer Service:

​

This area is not connected to public sewer and the project will have no impact on the public sanitary system.

Schedule

Design:

 

Phase 1 design contract was awarded to Dewberry Engineers in April 2023.

​

Construction:

 

Construction is expected to start in the Summer of 2024 and is expected to be completed by the Spring of 2025.

​

Next Phase:

 

Phase 2 Design is expected to start in the Summer 2024 and Construction is expected to start in the Fall 2025. For more information see MD 247 Loveville Road Water Main Replacement Phase 2 under design projects.

Public Notices

Public Meeting:

 

A Public Information Workshop will be held on Tuesday, March 5, 2024, from 4:30 p.m. to 5:30 p.m. in the Main Conference Room of MetCom’s Administrative Office – 23121 Camden Way, California, MD 20619 at which time the proposed contract documents, including plans and specifications, can be inspected.  or at MetCom’s Engineering Department, office location noted above, by appointment from 8:00 AM to 3:00 PM Monday through Friday. 

All interested persons are invited to attend this Public Workshop.

Project Location

MD247 Loveville Road WM Location Map.jpg

Project Contacts

Joshua Woodburn – METCOM Project Manager: (301) 737 – 7400 x 307

(Please email any questions or concerns to jwoodburn@metcom.org)

​

Ronald Delahay – METCOM Senior Inspector: (240) 298 – 0074 

​

Chris Soussanin – METCOM Chief of Construction: (301) 737 – 7400 x 311